Introduction

The uploads panel within the Project Details page allows you to see a history of data imports on a project. It also allows you to download the original import file (where applicable) and delete an upload to remove all interviews added by that upload.


Accessing the uploads panel

To view the uploads panel, click the "Uploads" button in the ribbon within the Project Details page.



Panel columns

The uploads panel displays a table of information containing the following columns:


ColumnDescription
Start TimeThe date and time that an upload began the importing
End TimeThe date and time that an upload completed importing
Upload TypeThe type of upload, either "File" or "Data Sync"
No. of RespondentsThe number of new interviews added by the upload
No. of ResponsesThe number of data points (e.g. non-blank Excel cells) added by the upload
No. of Responses OverwrittenThe number of data points overwritten in codeit by the upload
StatusThe current status of the import. Either "In Progress", "Complete" or "Failed"
Imported FileButton allowing you to download the original uploaded file (where applicable)
Delete SessionButton allowing you to delete an upload and thus delete any interviews added by that upload